Nuclear Waste

Toronto Star editorial
22 Jun 2008

Critics of the provincial government's decision to expand the Darlington nuclear station have zeroed in not on safety or environmental concerns but on potential cost overruns.

The original Darlington plant, completed in 1993, was "wildly overbudget," said Lawrence Solomon of the anti-nuclear Energy Probe, citing an original cost estimate of $2.5 billion and comparing it with the final bill of $14.4 billion.  read more »

21 Jun 2008

 

On Saturday, June 21, Norman Rubin of Energy Probe appeared on Global TV's "Focus Ontario" to discuss the proposed Darlington B new nuclear build with host Sean Mallen and Murray Elston of the Canadian Nuclear Association (CNA).

The appearance in full is captured at the Focus Ontario website, listed here:
www.canada.com/globaltv/ontario/features/focus_ontario/video.html